Rajasthan Solar – Status of projects commissioned as of 30 June 2013

With the commissioning of the first CSP plant allotted under the JNNSM Phase 1, the total solar installed capacity in Rajasthan has reached 608.5 MW. During the period April 2013 to June 2013, a total of 55.75 MW was commissioned in the state. An analysis of the projects commissioned till March 2013 can be found here. The latest status as per Rajasthan Renewable Energy Corporation Limited(RRECL) is given below.

Jodhpur continues to be the top district in terms of the number of projects(47) and total installed capacity(334 MW).
Districtwise July 2013
In fact, Jodhpur is the number one district across the country with the most number of projects. Patan and Surendranagar districts in Gujarat follow. Jaisalmer in Rajasthan comes 4th and Kutch district in Gujarat comes 5th. The district-wise project details in Gujarat are given below. (More details of projects in Gujarat are available in our whitepaper on the First Ranking of Solar Plants in Gujarat here).
Gujarat districtwise projects
The details of the projects in Rajasthan are available in the RRECL website here.
___________________________________________________________________________________________
Subscribe to RESolve Energy Consultants : Perspectives and Insights by Email
___________________________________________________________________________________________