CERC Benchmark Costs

  Particulars(In Crores/MWp) 2013-14 2014-15 2015-16 2016-17
1 PV Modules 3.2592 3.658 3.3235 3.2839
2 Land Cost 0.168 0.25 0.25 0.25
3 Civil and General Works 0.945 0.6 0.5 0.35
4 Mounting Structures 1.05 0.5 0.5 0.35
5 Power Conditioning Units/Inverters 0.6 0.5 0.45 0.35
6 Evacuation Cost upto inter-connection point (cables and transformers) 1.05 0.6 0.55 0.44
7 Preliminary and pre-operative expenses including IDC and contigency 0.8 0.69 0.485 0.2763
8 Others 0.098 0.110
Total(In Crores/MWp) 7.97 6.91 6.0585 5.3002

Source : CERC